N02. Between Maya and Fortana blocks

Building / block / estate

N02 Fortuna House, Karner House, Meander House, Zeller House

Address

Plot N02 Zone 5 Stratford City
Victory Parade / Honour Lea Avenue / Logan Close / Napa Close

Local Authority

Newham. https://pa.newham.gov.uk/online-applications

Storeys / height

10

Cladding

Pre-cast. ACM

Owner / Landlord

Get Living

Original design architect

KDS Associates

Limited information on Newham portal

Remediation ref/date

-

Remediation lead

-

Litigation

https://www.judiciary.uk/wp-content/uploads/2024/01/Triathlon-Homes-LLP-v-Stratford-Villa-Development-Partnership-and-others-judgment.pdf

Triathlon Homes v Stratford Village Development Partnership

  1. The Grenfell Tower fire in June 2017 precipitated a review by EVML of the cladding materials utilised at East Village. The initial investigation took the form of desk top studies and concentrated on identifying the presence of the ACM cladding which had been implicated as a primary cause of the rapid spread of the fire at Grenfell. The buildings at East Village were, for the most part, clad in masonry, including brick and pre-cast concrete, but ACM material was soon found to have been used in limited locations on eight buildings in Plots N02 and N07 but not in Plot N26. The design and implementation of a remedial scheme to remove this ACM cladding was EVML’s first priority and removal was completed by January 2021, but it soon appreciated that there were more widespread problems. The earliest issue to be suspected at Plot N26 related to compartmentation which was reported to the board as being under investigation in May 2018.
Link to original


14/00010/AOD_LLDC - Variation to Zonal Masterplan. Approved 28/02/2014


N26 blocks (Meller House, Chroma Mansions, Seasons House, Patina Mansions, Kaleidoscope House) - the main subject of Triathlon Homes v Stratford Village Development Partnership

13_00484_AOD_LLDC-DRAWING_ALD617-PL402_REV01-3709716