- Spectrum Building (formerly Spectrum House) - Remediation design lead: GA and A DESIGN (Mr Sundeep Bhavra) - agent on the 2023 remediation application 23/00663/FULL, received 02/05/2023, for removal of existing non-compliant cladding and replacing with compliant cladding
Source / Evidence / Links
- (Other remediation, row 50)
Additional corroboration (Practices tab)
- Spectrum Building (formerly Spectrum House), Spectrum - REMEDIATION designer
Basis: Agent on remediation application 23/00663/FULL, 02/05/2023. The building then suffered a MAJOR FIRE on 26/08/2024, is subject to an HSE investigation and is to be demolished. Known safety issues since 2020. Professional status of the firm not established